Planning Material Requirements For Your Dream Home

It is important to plan material requirements for your dream home as accurately as possible to minimize wastage as well as insufficiency of material during construction. Here are some thumb rules to consider while planning material requirements of your dream home.

Reinforced Cement Concrete (RCC) Work

Material requirement for 1 cubic meter of RCC is given in the table below.

RCC Work

Concrete Mix: M25 (1:1:2 approx.)

Water and Cement Ratio 0.35
Water (Liter per Bag of Cement) 17.5
Cement (Bags) 11.2
Sand Stone (Cubic Meter) 0.40
Aggregates (Cubic Meter) 0.80
Steel Rebar (Kg) 80-120

Concrete Mix: M20 (1:1.5:3 approx.)

Water and Cement Ratio 0.42
Water (Liter per Bag of Cement) 21.0
Cement (Bags) 8.0
Sand Stone (Cubic Meter) 0.42
Aggregates (Cubic Meter) 0.83
Steel Rebar (Kg) 75-115

Concrete Mix: M15 (1:2:4 approx.)

Water and Cement Ratio 0.55
Water (Liter per Bag of Cement) 27.5
Cement (Bags) 6.2
Sand Stone (Cubic Meter) 0.43
Aggregates (Cubic Meter) 0.87
Steel Rebar (Kg) 70-110

Note :

Indian Code IS 456:2000 has recommended that minimum grade of concrete for PCC and RCC is M 20 (1:1.5:3 approx)

Brickwork Material Estimation

Material Requirement for 1 cubic meter of brickwork for various mortar mixes are given in the table below.

Brickwork

Mortar 1:3 1:4 1:6
Cement (Bags) 2.6 1.9 1.4
Sand (Cubic Meter) 0.267 0.275 0.299
No. of Bricks 500 500 500

Plaster Work Material Estimation

Material requirement for 100 square meter of plaster of 12 mm (1/2 inch) thick is given in the table below.

Plaster Work

Mortar Cement (Bags) Sand (Cubic Meter)
1:2 21 1.4
1:3 15 1.5
1:4 12 1.6
1:6 9 1.8

Note :

Add about 5% more material for wastage in all estimates.