Following are few general points to remember for civil site engineers to make the construction work easier while maintaining quality of construction.
- Lapping is not allowed for the bars having diameters more than 36 mm.
- Chair spacing : Maximum spacing is 1.00 m (or) 1 No. per 1 m2.
- For dowels rod minimum of 12 mm diameter should be used.
- Chairs minimum of 12 mm diameter bars to be used.
- Longitudinal reinforcement not less than 0.8% and more than 6% of gross C/S.
- Minimum bars for square column is 4 No’s and 6 No’s for circular column.
- Main bars in the slabs shall not be less than 8 mm (HYSD) or 10 mm (Plain bars) and the distributors not less than 8 mm and not more than 1/8 of slab thickness.
- Minimum thickness of slab is 125 mm.
- Dimension tolerance for cubes + 2 mm.
- Free fall of concrete is allowed maximum to 1.50 m.
- Lap slices not be used for bar larger than 36 mm.
- Water absorption of bricks should not be more than 15 %.
- pH value of the water should not be less than 6.
- Compressive strength of Bricks is 3.5 N / mm2.
- In steel reinforcement binding wire required is 8 kg per MT.
- In soil filling as per IS code, 3 samples should be taken for core cutting test for every 100 m2.
Density of Materials:
- Bricks : 1600 – 1920 kg/m3
- Concrete block : 1920 kg/ m3
- Reinforced concrete : 2310 – 2700 kg/ m3
Curing time of RCC Members for different types of cement:
- Super Sulphate cement: 7 days
- Ordinary Portland cement OPC: 10 days
- Minerals & Admixture added cement: 14 days
De-Shuttering time of different RCC Members
- For columns, walls, vertical form works : 16-24 hrs.
- Soffit formwork to slabs : 3 days (props to be refixed after removal)
- Soffit to beams props : 7 days (props to refixed after removal)
- Beams spanning upto 4.5m : 7 days
- Beams spanning over 4.5m : 14 days
- Arches spanning up to 6m : 14 days
- Arches spanning over 6m : 21 days
Cube samples required for different quantity of concrete:
- 1 – 5 m3 : 1 No’s
- 6 – 15 m3 : 2 No’s
- 16 – 30 m3 : 3 No’s
- 31 – 50 m3 : 4 No’s
- Above 50 m3 : 4 + 1 No’s of addition of each 50 m3